Home » Critical Path Method (projects)

Critical Path Method (projects)

1957
  • Morgan R. Walker
  • James E. Kelley Jr.
Project manager analyzing Gantt chart for skyscraper construction using Critical Path Method.

The Critical Path Method (sometimes referred as CPM, confusing in many domains) is a methodology for scheduling project activities. It identifies the longest stretch of dependent tasks (the ‘critical path’) and measures the time required to complete them from start to finish. Any delay in a task on the critical path directly impacts the project’s completion date -targeted parameter here is date, not cost, nor quality, nor resources, although none of these are independent-. It helps consequently in resource allocation and schedule optimization.

Developed in the late 1950s by Morgan R. Walker of DuPont and James E. Kelley Jr. of Remington Rand, the Critical Path Method (CPM) was created to manage complex industrial projects, initially for the maintenance of chemical plants. Its novelty lies in its use of network analysis to model a project’s workflow. The process begins by identifying all project activities, determining their sequence and dependencies, and estimating the duration of each. This information is used to construct a project network diagram, which visually represents tasks as nodes and dependencies as connecting arrows.

The core of CPM is the calculation of the ‘critical path’. This is achieved through a forward pass and a backward pass through the network. The forward pass calculates the earliest start and finish times for each activity, while the backward pass determines the latest start and finish times. The ‘float’ or ‘slack’ for each activity—the amount of time it can be delayed without affecting the project’s final deadline—is then calculated by subtracting the earliest finish time from the latest finish time. Activities with zero float are on the critical path. Any delay to these critical tasks will delay the entire project. CPM is a deterministic model, meaning it uses single, fixed time estimates for each task. This contrasts with its contemporary, PERT (Program Evaluation and Review Technique), which uses a probabilistic three-point estimate (optimistic, pessimistic, most likely) to account for uncertainty. CPM provides managers with a powerful tool to focus their attention on the most crucial tasks, optimize resource allocation, and perform ‘what-if’ analysis to assess the impact of potential delays.

UNESCO Nomenclature: 5312
– Management sciences

Type

Methodology

Disruption

Substantial

Usage

Widespread Use

Precursors

  • Gantt charts
  • Network flow analysis
  • Graph theory
  • Operations research development during WWII

Applications

  • large-scale construction projects (skyscrapers, bridges)
  • aerospace and defense projects
  • software development and it infrastructure rollouts
  • manufacturing plant shutdowns and maintenance
  • research and development projects
  • oil and gas exploration and production

Patents:

NA

Potential Innovations Ideas

Professionals (100% free) Membership Required

You must be a Professionals (100% free) member to access this content.

Join Now

Already a member? Log in here
Related to: critical path method, CPM, project management, scheduling, network diagram, critical path, float, slack, task dependency, operations research.

Leave a Reply

Your email address will not be published. Required fields are marked *

AVAILABLE FOR NEW CHALLENGES
Mechanical Engineer, Project, Process Engineering or R&D Manager
Effective product development

Available for a new challenge on short notice.
Contact me on LinkedIn
Plastic metal electronics integration, Design-to-cost, GMP, Ergonomics, Medium to high-volume devices & consumables, Lean Manufacturing, Regulated industries, CE & FDA, CAD, Solidworks, Lean Sigma Black Belt, medical ISO 13485

We are looking for a new sponsor

 

Your company or institution is into technique, science or research ?
> send us a message <

Receive all new articles
Free, no spam, email not distributed nor resold

or you can get your full membership -for free- to access all restricted content >here<

Historical Context

(if date is unknown or not relevant, e.g. "fluid mechanics", a rounded estimation of its notable emergence is provided)

Related Invention, Innovation & Technical Principles

Scroll to Top

You May Also Like