Takt time is a theoretical calculation representing the pace of customer demand ([latex]Available Time \div Demand[/latex]). In contrast, cycle time is an empirical measurement of the actual time taken to complete one unit of work at a specific process step. A core principle of lean manufacturing is to ensure that cycle time is consistently less than or equal to Takt time.
Distinction Between Takt Time and Cycle Time
The relationship between Takt time, cycle time, and lead time is critical. Takt time is what you need, cycle time is what you get, and lead time is the total time a customer must wait for a product. The primary diagnostic use of this distinction is in line balancing and bottleneck identification. By measuring the cycle time of every station on a line and comparing it to the Takt time, managers can instantly see where problems lie. Any station where Cycle Time > Takt Time is a bottleneck that constrains the entire system’s output. Efforts for improvement, or ‘kaizen’, should be focused on these bottleneck stations to reduce their cycle time.
Conversely, if a station’s Cycle Time < Takt Time, it has spare capacity. While this may seem good, it can lead to overproduction if not managed. The operator may finish their work early and produce extra units ‘just in case’, creating inventory that is not yet needed by the next station or the customer. The lean ideal is to balance the line so that the cycle time of each station is very close to, but just under, the Takt time. This creates a smooth, synchronized flow and maximizes labor efficiency without generating wasteful inventory.
Tipo
Disruption
Utilizzo
Precursors
- the theory of constraints developed by Eliyahu M. Goldratt
- development of performance metrics in industrial settings
- the concept of a bottleneck in production theory
- controllo statistico di processo methods for measuring process times
Applicazioni
- bottleneck analysis and management
- production capacity planning
- performance measurement for manufacturing cells
- guiding continuous improvement (kaizen) activities
- work balancing across multiple stations
Brevetti:
Potential Innovations Ideas
Livelli! Iscrizione richiesta
Per accedere a questo contenuto devi essere un membro di !Professionals (100% free)!
DISPONIBILE PER NUOVE SFIDE
Mechanical Engineer, Project, Process Engineering or R&D Manager
Disponibile per una nuova sfida con breve preavviso.
Contattami su LinkedIn
Plastic metal electronics integration, Design-to-cost, GMP, Ergonomics, Medium to high-volume devices & consumables, Lean Manufacturing, Regulated industries, CE & FDA, CAD, Solidworks, Lean Sigma Black Belt, medical ISO 13485
Stiamo cercando un nuovo sponsor
La tua azienda o istituzione si occupa di tecnica, scienza o ricerca?
> inviaci un messaggio <
Ricevi tutti i nuovi articoli
Gratuito, no spam, email non distribuita né rivenduta
oppure puoi ottenere la tua iscrizione completa -gratuitamente- per accedere a tutti i contenuti riservati >Qui<
Historical Context
Distinction Between Takt Time and Cycle Time
(if date is unknown or not relevant, e.g. "fluid mechanics", a rounded estimation of its notable emergence is provided)
Related Invention, Innovation & Technical Principles